1
What is the formula for commited utilization?
Allocated hours/capacity
2
How many days is the default sprint length if the length cannot be calculated from the sprint?
14
3
What role is required to view the Details tab of project in Project Workspace?
it_project_user
4
Risk and issuesé sublitted i which forms will be included in the program record?
project
demand
program
5
the program management application provides the Following capabilities to the program manager ( choose three)
create tasks specific to the program
track program costs
create a program by adding related projects and demands
6
which feature provides a central location for portfolio managers to create and track the roadmap for project and demand execution?
Portfolio Workbench
7
Why is it recommended to keep the value of the property to 2600 or Under?
to avoid application memory issues
8
which role can create a project status in the project Workspace?
it_project_manager
9
when creating a program, which of the Following cannot be part of multiple programs?
project
demand
10
Which role allows you to allocate a resource?
resource_manager
11
Wy would a program manager create a program?
to manage related demands
to manage related projects
12
which role in project portfolio management contains booth the resource_user and it_demand manager roles?
it_project_manager
13
if you want the project planned start date to remain the same despite the start date of hte earliest task, what property would you disable?
roll up project start date from tasks[project time table]
14
which table stores daily capacity of a user?
resource_aggregate_daily
15
users with what role can be considered for resource planning?
pps_resource
16
what features are not included in a teamspace application but can be Added in teamspace settings?
Workbench configuration
demand assessments
17
is resource capacity derived from FTE or schedules?
only schedues
18
how is teh resource management application activated?
installed with ppm standard plugin
19
can an it_project_manager convert a task to a Milestone?
yes, from the planning console right-click a task and select convert to Milestone
20
which field on the Idea module form display theunique identifier for the modue, what is used as a parameter in the idea portal URL to direct users?
module ID
21
which users have access the project administration application? ( choose two)
it_pps_admin
it_project_manager
22
The business unit field on aproject or displays values from a specified table. what type of field is this?
reference
23
if an it_project_manager does not want to equally distribute hours across the resource plan time frame, what allocation spread should be used?
Front Load
24
using the request type field on a resource plan , which options can be used to request a resource? (choose three)
hours
fte
person days
hat are the possibe breakdown types of a cost plan breakdown? ( choose four)
requirement
task
portfolio
program
25
where is planned cost calculated from when requesting resources form a group and when resource role is specified?
The hourly rate of the specified role
26
what is a program?
a group of related projects, demands, and program activities
27
what role can configure the default colulns in the project planning console? (Choose two)
admin
it_pps_admin
28
what is the minimum role that has access to the project administration/setting/preferences-project module?
it_pps_admin
29
when creating a project from demand, what related records are moved and copied upon project creation?
resource plan and cost plan
30
how many wbs levels can be shown on the planning console?
no limit
31
what is a data copy of the current project's task, Schedule, or structure that can be used for comparison reporting later?
Baseline
32
a checklist item record provides a name and what other element?
Complete field
33
the project property to update actual effort from time card is controlled at what level?
application Level(Global)
34
what is a resource event?
a block of time that a resource spends on a task
35
what happens to resource allocations with actual hours after a resource plan is cancelled?
the allocated hours become zero and the actual hours are retained
36
a program is a container for the Following except for:
portfolios
37
which related lists should primarly be used to capture Financial data in a project? choose two
cost plans
monetary benefit plans
38
use this table to configure the parameters displayed on aproject card on the My projects space page of the project Workspace
pm_home_page_config
39
which statement defines the project Workspace?
A CENTRAL LOCATION FOR CREATING AND MANAGING PROJECTS
40
A user's availability is calculated as
capacity minus allocation
41
A project expense line is cost associated wih a specific source, except for:
prohram