1
When copying a resource project to a target project, what fields are copied by default? (Choose three)
Duration fields
Short description
Planned dates
2
If a project manager is responsible for approving time sheets or submitting time cards on behalf of team members, they should be given what role?
timecard_admin
3
which property controls the changes in cost and resource plans with respect to the change in the start date of a demand or project?
Change Resource Plan , Cost Plan and Benefit Plan Start Date with Demand or Project Start Date Change
4
If the Move project for WIP projects propert is enabled, project tasks associated with the project are also moved, except for tasks in which of the Following states? (Choose two)
Closed
Work in Progress
5
Expenses and costs for a particular demand should be estimated before screening . when preparing the Financial of a demand, what determines the present value of future cash flows?
Discount Rtae %
6
Idea [im_idea_core] is directly extended from which table?
Task
7
The defect and Enhancement typr choices on a demand form are available only when which plugin is installed?
Agile development 2.0
8
The color band at the top of the project card in project Workspace displays what project attribute?
Status
9
As an administrator, what can you use to customize the PPM Mobile application?
Mobile Studio
10
Demand assessments are triggered as soon as the demand enters what state
Screening
11
If an it_project_manager does not want to equally distribute hours acorss the resource plan time frame
what allocation spread should be used?
Front Load
12
On the demand from, what does the Discount Rtae impact?
Net PresentValue (NPV)
13
As a demand manager, you can view an artifact from a demand. What artifacts are part of a demand?
Project , Defect, Requests
14
As an it_pps_admin, what can you use to detect corrupt data in a project, such as tasks with invalid paents or cyclic relations in a project?
Project Diagnostics
15
In which scenario would using teh copy project action Not result in a new project record being created?
When copying partial projects
16
Which of the Following can be used to calculate planned cost when creating a resource plan? (Choose two)
Default rate
Rate card
17
the project management application supports two types of external dependencies. what are they? (Choose two)
Hard dependency
soft dependency
18
In order to map custom fields from Microsoft Project to servicenow when importing a project, you must first:
Create custom fields in your Servicenow instance